中文幕亚洲精品乱码色偷偷亚_国产午夜性爽视频男人的天堂_欧美高潮流白浆喷水在线观看_亚洲夜色久一久二亚洲琪琪卡一卡二_暖暖亚洲一区二区三区AV无码

435-km-long Lhasa-Nyingchi railway expected to be completed in 2021

Source: Xinhua| 2019-08-03 21:55:23|Editor: huaxia
Video PlayerClose

Staff members work at the construction site of the Lhasa-Nyingchi section of the Sichuan-Tibet Railway in southwest China's Tibet Autonomous Region, on Dec. 23, 2018. (Xinhua/Chogo)

The Lhasa-Nyingchi railway is 435 km long, 75 percent of which are bridges and tunnels. It is expected to be completed in 2021.

LHASA, Aug. 3 (Xinhua) -- Construction on a pivotal tunnel on a railway linking Lhasa and Nyingchi in southwest China's Tibet Autonomous Region was completed Friday, marking huge progress of the mammoth project.

The Bukamu Tunnel, located in Milin County of Nyingchi, is 9,240 meters long with an average elevation of 3,100 meters above the sea level. It is also the 37th tunnel being finished, leaving just 10 tunnels to be completed by the end of the year.

Over 3,000 rock bursts were counted during the construction of the tunnel, while the oxygen level inside was merely 19 percent that of the plain areas, said Wang Shucheng, director of the project.

The Lhasa-Nyingchi railway is 435 km long, 75 percent of which are bridges and tunnels. It is expected to be completed in 2021.

KEY WORDS:
EXPLORE XINHUANET
010020070750000000000000011103261382814941